Component | %Weightage as per Schedule-G | Progress achieved (during current month) | Physical Progress achieved (Cumulative, up to current month) |
---|---|---|---|
Road works including culverts, minor bridges, underpasses, overpasses, approaches to ROB/RUB/ Major Bridges/ Structures (but excluding service roads) | 63.16% | 1.54% | 7.39% |
Major Bridge Works & ROB / RUB | 5.94% | 0.31% | 0.46% |
Electrical and Public Health Utilities | 0.95% | 0.03% | 0.88% |
Other Works | 29.95% | 0.63% | 2.03% |
Total | 100% | 2.51% | 10.76% |