| Component | %Weightage as per Schedule-G | Progress achieved (during current month) | Physical Progress achieved (Cumulative, up to current month) |
|---|---|---|---|
| Road works including culverts, minor bridges, underpasses, overpasses, approaches to ROB/RUB/ Major Bridges/ Structures (but excluding service roads) | 63.16% | 2.61% | 19.64% |
| Major Bridge Works & ROB / RUB | 5.94% | 0.48% | 2.85% |
| Electrical and Public Health Utilities | 0.95% | 0.00% | 0.90% |
| Other Works | 29.95% | 0.73% | 4.69% |
| Total | 100% | 3.82% | 28.08% |