Physical Progress

Physical Progress

Component %Weightage as per Schedule-G Progress achieved (during current month) Physical Progress achieved (Cumulative, up to current month)
Road works including culverts, minor bridges, underpasses, overpasses, approaches to ROB/RUB/ Major Bridges/ Structures (but excluding service roads) 63.16% 1.63% 9.02%
Major Bridge Works & ROB / RUB 5.94% 0.51% 1.12%
Electrical and Public Health Utilities 0.95% 0.00% 0.88%
Other Works 29.95% 0.58% 2.61%
Total 100% 2.71% 13.62%