Component | %Weightage as per Schedule-G | Progress achieved (during current month) | Physical Progress achieved (Cumulative, up to current month) |
---|---|---|---|
Road works including culverts, minor bridges, underpasses, overpasses, approaches to ROB/RUB/ Major Bridges/ Structures (but excluding service roads) | 63.16% | 1.63% | 9.02% |
Major Bridge Works & ROB / RUB | 5.94% | 0.51% | 1.12% |
Electrical and Public Health Utilities | 0.95% | 0.00% | 0.88% |
Other Works | 29.95% | 0.58% | 2.61% |
Total | 100% | 2.71% | 13.62% |