| Items | % Weightage as per Annexure-I of Schedule – G | % Physical Progress (in Previous month) (A) |
% Physical Progress (Current month) (B) |
% Cumulative Physical Progress (C = A + B) |
|---|---|---|---|---|
| Road works including culverts, minor bridges, underpasses, overpasses, approaches to ROB/RUB/ Major Bridges/ Structures (but excluding service roads) | 63.16% | 41.66% | 3.13% | 44.79% |
| Major Bridge Works & ROB / RUB | 5.94% | 3.39% | 0.22% | 3.61% |
| Electrical and Public Health Utilities | 0.95% | 0.90% | 0.00% | 0.90% |
| Other Works | 29.95% | 11.58% | 0.71% | 12.29% |
| Total | 100.00% | 57.53% | 4.05% | 61.59% |