| Project Milestone | As per Concession Agreement | Revised Scheduled as per Settlement Agreement | As per recommended EOT, Completion Date (EOT 167 days) | Actual | Delay (No. of months) | Current Status | Remarks (Letter or Comment Ref., if any) | ||||
|---|---|---|---|---|---|---|---|---|---|---|---|
| No. of days from the AD | Physical Progress to be achieved (%) |
Scheduled Date | No. of days from the AD | Physical Progress achieved (%) |
Actual Achieved Date |
||||||
| Milestone-I | 160 | 20.00% | 11.03.2025 | 334 | 20.00% | 02.09.2025 | – | Achieved | i.Concessionaire notified vide letter no. 562, dated 06.09.2025 ii. IE’s (Letter no. 310 dated 12.09.2025) |
||
| Milestone-II | 360 | 35.00% | 27.09.2025 | 26.03.2026 | 485 | 35.00% | 22.01.2026 | – | Achieved | i.Concessionaire notified vide letter no. 719, dated 07.02.2026 ii. IE’s (Letter no. 410 dated 22.01.2026) |
|
| Milestone-III | 500 | 75.00% | 14.02.2026 | 15.05.2026 | 29.10.2026 | 65.42% | InProgress | The Concessionaire, vide Letter No. 894 dated 11.08.2026, proposed an Extension of Time (EOT) of 210 days. The Independent Engineer (IE), vide Letter No. 617 dated 14.09.2026, recommended an Extension of Time (EOT) of 167 days. Subsequently, the Authority, vide Letter No. 2010 dated 29.09.2026, recommended the same to RO Mumbai for further consideration and approval. Based on the PIU’s recommendation of an EOT of 167 days | |||
| Scheduled Completion Date | 730 | 100.00% | 02.10.2026 | 02.10.2026 + Grace Period | 18.03.2027 | ||||||