Project Milestone Status

Project Milestones Status

Project Milestone As per Concession Agreement Revised Scheduled as per Settlement Agreement As per recommended EOT, Completion Date (EOT 167 days) Actual Delay (No. of months) Current Status Remarks (Letter or Comment Ref., if any)
No. of days from the AD Physical
Progress to be achieved
(%)
Scheduled Date No. of days from the AD Physical
Progress achieved
(%)
Actual Achieved
Date
Milestone-I 160 20.00% 11.03.2025     334 20.00% 02.09.2025 – Achieved i.Concessionaire notified vide letter no. 562, dated 06.09.2025
ii. IE’s (Letter no. 310 dated 12.09.2025)
Milestone-II 360 35.00% 27.09.2025 26.03.2026   485 35.00% 22.01.2026 – Achieved i.Concessionaire notified vide letter no. 719, dated 07.02.2026
ii. IE’s (Letter no. 410 dated 22.01.2026)
Milestone-III 500 75.00% 14.02.2026 15.05.2026 29.10.2026   65.42%    InProgress The Concessionaire, vide Letter No. 894 dated 11.08.2026, proposed an Extension of Time (EOT) of 210 days. The Independent Engineer (IE), vide Letter No. 617 dated 14.09.2026, recommended an Extension of Time (EOT) of 167 days. Subsequently, the Authority, vide Letter No. 2010 dated 29.09.2026, recommended the same to RO Mumbai for further consideration and approval. Based on the PIU’s recommendation of an EOT of 167 days
Scheduled Completion Date 730 100.00% 02.10.2026 02.10.2026 + Grace Period 18.03.2027